Quote:
The Department of Transport has also conceded that there is no operable date for a joining of the two Luas lines in Dublin city centre, following concerns expressed by Dublin Bus about the impact on bus traffic. The link-up was due to be finished next year.
They can delay that one in to oblivion for all I care. Expensive pile of RPA nonsense.

Delays seem to be on the rail side, all interurban mortorways are either on time or ahead of schedule. Priorities.

Last edited by Peter FitzPatrick : 08-11-2007 at 13:26.
Peter FitzPatrick is offline  
Unread 11-11-2007, 20:46   #2
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Quote:
Originally Posted by Peter FitzPatrick View Post
Delays seem to be on the rail side, all interurban mortorways are either on time or ahead of schedule.
Well insofar as they were all meant to be finished at the end of 2006 ....
Colm Moore is offline  
Unread 12-11-2007, 09:09   #3
Brian Condron
Member
 
Join Date: Jun 2006
Posts: 268
Default

Quote:
Originally Posted by Victor View Post
Well insofar as they were all meant to be finished at the end of 2006 ....
Where does this 2006 figure that is thrown around come from? To the best of my knowledge, the original plan was for a series of by-passes around the country's biggest bottle necks. Then a few years ago the plan was changed to have brand new motorways/hqdcs between the major urban centres. Is the 2006 figure the one for completing all the by-passes?

Anyway, we have been building roads at a phenomenal rate in this country, I can't see how we could have built them any quicker. There are only so many road construction contractors in Europe, let alone Ireland.
Brian Condron is offline  
Unread 12-11-2007, 09:31   #4
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Well by 2006 we should have had the Metro to Dublin Airport and would be just starting to dig for the line to Navan. Kildare route project would be half done etc

Every single rail project is running late, they all started late due to planning issues which in all cases relate to the minister either not signing the order in reasonable time or the DoT demanding a scale back before committing
Mark Gleeson is offline  
Unread 12-11-2007, 15:48   #5
Peter FitzPatrick
New to the board
 
Join Date: Mar 2006
Location: Dublin
Posts: 26
Default

Quote:
Originally Posted by Victor
Well insofar as they were all meant to be finished at the end of 2006 ....
True Victor, the inter-urbans were part of the last National Development Plan. It was fairly clear early on there wasn't a chance that deadline could be met once the land acquisition process started & fairly quickly ran in to a brick wall, never mind swans & snails.

The point is we are building a national motorway network in 5 years, & despite the usual guff about delays from media etc. that is pretty damn fast.

In the mean time, on the rail side, we have two luas lines & a slow renewal of rolling stock / signalling.

It’s clear what Government policy is; pay lip service to rail, build roads like the clappers.

Even in a so called bad year, Government will turn a surplus of 6 billion euro this December; essentially they are building our infrastructure out of change in Cowen's back pocket.

Why they cannot borrow & accelerate the rail agenda with even a portion of the vigour constructing the motorway network receives is beyond me. There is no reason, financial or otherwise, why Government can't do the same for rail as they are doing for roads, both could move forward in tandem if the will was there.

Last edited by Peter FitzPatrick : 12-11-2007 at 15:52.
Peter FitzPatrick is offline  
Closed Thread


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 20:03.


Powered by vBulletin
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.