One story I heard (maybe not true, but totally believable) was that work on the connecting footbridge was delayed because of a dispute between Irish Rail and Transport Infrastructure Ireland about who should pay what share of the cost.

Pathetic, but totally credible.
ACustomer is offline   Reply With Quote
Unread 10-12-2017, 15:10   #2
Jamie2k9
Really Really Regluar Poster
 
Join Date: Jun 2010
Posts: 2,146
Default

Irish Rail have nothing to do with construction (not that they would of managed it on time either!), its the NTA or TII who are in charge of it and they had 4 years.

Quote:
One story I heard (maybe not true, but totally believable) was that work on the connecting footbridge was delayed because of a dispute between Irish Rail and Transport Infrastructure Ireland about who should pay what share of the cost.

Pathetic, but totally credible.
Not sure about the dispute but I agree IE shouldn't have to fund the project. After all it's part of Luas project. For example it was Luas/TII/NTA who fund access to Connolly station and maintain it today.

Last edited by Jamie2k9 : 10-12-2017 at 15:13.
Jamie2k9 is offline   Reply With Quote
Unread 11-12-2017, 09:25   #3
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

There has been a long standing turf war over the Broadstone - Broombridge section, Irish Rail & CIE did there best to invent a fictitious need to use Broadstone as a rail terminus again

The footbridge design is a standard Irish Rail footbridge with lift modular design not the design shown in the planning documents for Luas cross city which suggests the project is under Irish Rail control.
Mark Gleeson is offline   Reply With Quote
Unread 11-12-2017, 11:36   #4
Jamie2k9
Really Really Regluar Poster
 
Join Date: Jun 2010
Posts: 2,146
Default

Quote:
Originally Posted by Mark Gleeson View Post
There has been a long standing turf war over the Broadstone - Broombridge section, Irish Rail & CIE did there best to invent a fictitious need to use Broadstone as a rail terminus again

The footbridge design is a standard Irish Rail footbridge with lift modular design not the design shown in the planning documents for Luas cross city which suggests the project is under Irish Rail control.
Maybe so but I don't think IE are paying anything so the money row could well be the reason for the delay.
Jamie2k9 is offline   Reply With Quote
Unread 11-12-2017, 13:08   #5
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Should be fully funded by the NTA
Mark Gleeson is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 18:25.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.