#41 |
Regular Poster
Join Date: Feb 2012
Location: Roscrea
Posts: 89
|
![]() No one said the early morining train was going ,
-Rumours at this stage seem to be suggesting that morning timetable wont change ,same amount of services , (plus direct train) and at Different times. but for the evening there will be only 1 service out from limerick and back in again, -which wouldnt be a bad idea . |
![]() |
![]() |
![]() |
#42 |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
![]() Unless things have changed Limerick Junction/Waterford is to loose a train in each direction leaving a service each way, morning and evening only.
Some reductions in frequency proposed on the Waterford/Dublin line, in particular the 0600 Waterford to Dublin is reportedly to be cancelled on Saturdays. Certainly the expectation is for reduced frequencies on other Heuston routes although I haven't heard any detail of these. |
![]() |
![]() |
![]() |
#43 | ||
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() Quote:
Quote:
Last edited by Jamie2k9 : 04-11-2012 at 16:09. |
||
![]() |
![]() |
![]() |
#44 |
Really Regular Poster
Join Date: Jan 2006
Posts: 767
|
![]() Cutting the Limerick-Junction waterford services to 2 each way would be bad news. Given that at present one 2800 set can do 3 return journeys per day, where is the saving? The main thing I can think of is that all the gatekeepers and signalmen might be retuced to one split shift. However with no Sunday service you will have very few trains and all those overheads: not looking good, for a line that has potential, if only management had some imagination and just a little marketing talent.
|
![]() |
![]() |
![]() |
#45 |
Member
Join Date: Dec 2008
Location: ar an traein
Posts: 602
|
![]() Not for one minute do I support reducing the service from three to two trains each way but I wonder if the savings such a scenario would achieve could allow a "trade off" of sorts in the provision of one Sunday train each way (Sunday late-afternoon/evening).
Such a move would generate extra business (the student, returning worker and short break market precluded from using rail by the current lack of a Sunday service). |
![]() |
![]() |
![]() |
#46 |
Really Really Regluar Poster
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
|
![]() I suspect any savings on the LJ-Waterford line will be of a strictly one-way-street variety. As for potential, the only hope for that line is that IE do something with it before the N24 gets improved. The Nenagh/Roscrea branch has the much stiffer challenge of the M7 to contend with.
Is there any possibility that similar speed limit raises are contemplated across the board, so that for example morning Waterford-Limerick Junction service could continue to reach the Junction ahead of an accelerated 0730 ex Cork? |
![]() |
![]() |
![]() |
#47 | |
Member
Join Date: Oct 2006
Posts: 395
|
![]() Quote:
- Cherryville - Athy (perhaps further) - Lavistown Jct towards Waterford |
|
![]() |
![]() |
![]() |
#48 |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() Trains are still doing no more than 80mph on Monday. As far as I know its mainly 100 apart form Lavistown Jct and Thomastown-Waterford.
|
![]() |
![]() |
![]() |
#49 | |
Member
Join Date: Oct 2006
Posts: 395
|
![]() Quote:
It's still 80mph between Carlow (?) or Muine Beag and Lavistown. |
|
![]() |
![]() |
![]() |
#50 | |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() Quote:
|
|
![]() |
![]() |
![]() |
#51 |
Really Regular Poster
Join Date: Jan 2006
Posts: 767
|
![]() If Limerick Jcn-Waterford loses its middle of the day services, then a 2800 railcar will be sitting in Waterford between about 1040 and 1640. Not exactly a brilliant way of using resources.
|
![]() |
![]() |
![]() |
#52 |
Member
Join Date: Dec 2008
Location: ar an traein
Posts: 602
|
![]() Not sure if this would be feasible...
In the Waterford - Clonmel - Limerick Junction two train each way scenario - wonder would it be possible to advance the first train (ex Waterford) by about an hour to 05.40/05.30 so that instead it would connect at the Junction into the 06.15 ex Cork train (it connects with the 07.30 ex Cork at present). In turn this would see it depart the Junction a tad after 07.00 thus providing an useful commuter link into Waterford. The evening departure could be adjusted to circa 17.30 ex Waterford. Downside is that there would be no link from the Dublin direction first thing in the morning but this would be by far outweighed in a positive sense by the provision of a service into Waterford which realistically can significantly tap the commuter market. It would allow a pre-0900 arrival into Dublin and a slightly longer day there too. Checks two key boxes in my view. |
![]() |
![]() |
![]() |
#53 | |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() http://www.independent.ie/national-n...f-3291881.html
Quote:
According to boards trail services serving Athy-Waterford was done in 2 hours so allow crossovers then max it should be is 2h06m based on two crossings. Then services stopping in Kildare/Newbridge should have 2h12m max based on two crossings also. 18.05 on Sundays operates in 2h15m with two crossings as could most others I do be on. Then this could just be more poor research from the Indo as before... Last edited by Jamie2k9 : 13-11-2012 at 17:42. |
|
![]() |
![]() |
![]() |
#54 |
Really Regular Poster
Join Date: Dec 2005
Location: Cork-Dublin, Cork Commuter and occasionally DART and Dublin-Wexford
Posts: 855
|
![]() Did the Indo actually read the timetable before publishing that? 2h 30 is already the speed of the fastest Cork-Dublin train.
|
![]() |
![]() |
![]() |
#55 |
Chairman/Publicity
Join Date: Dec 2005
Location: The Home of Hurling
Posts: 2,708
|
![]() its now 80 mph through ballybrophy
|
![]() |
![]() |
![]() |
#56 |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() Noticed a lot of new tracks in the sidings at Charleville including 4 sets of points.
Also Cork station looks to be facing a 7-10 day closure (Cork-Dublin services only) in the new year for works. From a conversation I overheard it will cost IE a lot of money and its a serous problem. Not going to post as I didn't hear eveything but its with the tunnel. Last edited by Jamie2k9 : 05-12-2012 at 18:54. |
![]() |
![]() |
![]() |
#57 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
![]() Lets keep away from things which were overheard, 99% of it is rubbish and you have no idea of the context
I've lost count of the number of rumors in the past, we are aware of Irish Rail spreading stories to staff to see where it leaks to,
__________________
Unhappy with new timetable - let us know |
![]() |
![]() |
![]() |
#58 |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
![]() You may be correct but the part I heard dosn't sound like it was made up or IE staff made up some fine details about it. We will just have to wait and see.
|
![]() |
![]() |
![]() |
#59 |
Really Really Regluar Poster
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
|
![]() If IE was to close for 7-10 days the Christmas Day-New Years Day period is when it should be happening. Wasn't that how it was done when they dealt with Dun Laoghaire's slab track?
Of course, if this had been built (with a crossover) maybe it wouldn't be quite such a big deal to do it, though train storage might have meant some truncations to Mallow and early morning deadheads. |
![]() |
![]() |
![]() |
#60 |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
![]() Mind you the slab track renewal was never finished - the northbound line has only been spot repaired while both lines at Sandycove station are still on concrete slabs.
Needless to say DART still limps along at 20 mph on both lines. |
![]() |
![]() |
![]() |