Default New Passing Loop between Cherryville - Athy?

Are IE putting a passing loop in about half way between Athy - Cherryville. They have layed stones and removed a gate crossing on the line. Where the works are taken place the area is just a little longer than a 6 car ICR set.

They have had a 25 speed limit over the last while.

If they are not putting one in what are they doing?

Its the only thing that they could be doing as they are not moving the main line. Its looking the exact same way whenn they were doing the loop at Ballyhale.

Last edited by Jamie2k9 : 18-09-2011 at 23:07.
Jamie2k9 is offline   Reply With Quote
Unread 19-09-2011, 07:03   #2
Inniskeen
Really Regular Poster
 
Join Date: Oct 2010
Posts: 951
Default

Quote:
Originally Posted by Jamie2k9 View Post
Are IE putting a passing loop in about half way between Athy - Cherryville. They have layed stones and removed a gate crossing on the line. Where the works are taken place the area is just a little longer than a 6 car ICR set.

They have had a 25 speed limit over the last while.

If they are not putting one in what are they doing?

Its the only thing that they could be doing as they are not moving the main line. Its looking the exact same way whenn they were doing the loop at Ballyhale.
I would be very surprised if a new loop were being provided between Cherryville Junction and Athy at this time. Long term, post celtic tiger revival (!), this section might be re-doubled so as to facilitate enhanced local services.

I would guess the work being described might relate to embankment stabilisation - what mileage is the work taking place at ?
Inniskeen is offline   Reply With Quote
Unread 19-09-2011, 08:48   #3
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

I very much doubt its a passing loop, if it was it would be much longer 350-400m

The cheap solution to capacity is an intermediate block signal as per Galway Athenry and Bray Greystones which allows two trains in the same direction in a single track section

Its probably elimination of a crossing and related works
Mark Gleeson is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 07:43.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.