Default Seapoint Station

After a 8 year wait work has finally got underway at Seapoint station

Sometime early on Sunday 7th December the foot bridge at Seapoint was craned out and a new temporary bridge was brought into use at the north end of the station

As is typical the original plans to build a proper modern station (which had planning permission) have been junked in favour of a cheap and nasty rebuild which will be incredibly tight on space.

Of course there is no notice on the Irish Rail website telling you this is ongoing, or of the rather long roundabout walk you have to make (its going to get longer shortly) to get to the southbound platform. And the notice at the station gives no indication of duration
Mark Gleeson is offline   Reply With Quote
Unread 15-12-2008, 13:40   #2
sublimity
Really Regular Poster
 
Join Date: Jan 2008
Location: Dublin
Posts: 309
Default

Quote:
Originally Posted by Mark Gleeson View Post
Of course there is no notice on the Irish Rail website telling you this is ongoing, or of the rather long roundabout walk you have to make (its going to get longer shortly) to get to the southbound platform. And the notice at the station gives no indication of duration
Irish rail website must be the worst national rail website in the world.
Good Seapoint is finally getting revamped
sublimity is offline   Reply With Quote
Unread 04-09-2009, 09:58   #3
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Looks like they are almost finished, so much for the March finish date

Hoarding finally came down on the southbound side this morning. The new bridge is complete and the lighting has been installed

The number of people walking across the track is getting crazy, the temporary bridge is interesting construction being lob sided and the steps not being flat
Mark Gleeson is offline   Reply With Quote
Unread 04-09-2009, 17:41   #4
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

New bridge finally is open, station building still not finished nor are the lifts or the platform displays
Mark Gleeson is offline   Reply With Quote
Unread 04-09-2009, 18:00   #5
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

If people are crossing the tracks, are enforcement or engineering measures needed?
__________________
Colm Moore is offline   Reply With Quote
Unread 04-09-2009, 18:05   #6
ThomasJ
Member
 
ThomasJ's Avatar
 
Join Date: Dec 2005
Location: Clonsilla
Posts: 2,812
Default

Quote:
Originally Posted by Victor View Post
If people are crossing the tracks, are enforcement or engineering measures needed?
Its difficult to do! At Clonsilla at the exit gate on the maynooth platform where there isnt much of a drop from the platform to the tracks people were constantly taking shortcuts! IEs answer was a few notices and blocking off this part of the platform.

It still happens though!

Of course there have been a few of these incidents at Castleknock in the past few weeks involving local youths crossing the tracks one of which forced the driver of a maynooth-bound commuter train to slow down and beep the horn repeatedly.
ThomasJ is offline   Reply With Quote
Unread 04-09-2009, 19:25   #7
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Quote:
Originally Posted by Victor View Post
If people are crossing the tracks, are enforcement or engineering measures needed?
No what they needed was a bridge that was located such as to give the shortest walk to the exit, we got that today only 5 months late
Mark Gleeson is offline   Reply With Quote
Unread 05-09-2009, 11:30   #8
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

There is a nasty step between the bridge and station building so watch out
Name:  Image031.jpg
Views: 5565
Size:  81.6 KBName:  Image030.jpg
Views: 5628
Size:  91.2 KBName:  Image028.jpg
Views: 5555
Size:  67.0 KBName:  Image027.jpg
Views: 5585
Size:  61.3 KB
Mark Gleeson is offline   Reply With Quote
Unread 05-09-2009, 15:59   #9
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Do you mean the lip I have circled here?

If thats what you mean, its probably against the Building Regualtions - all steps to be the same size and no "surprise" steps.

http://www.railusers.ie/forum/attach...5&d=1252166334
Attached Images
File Type: jpg Image030a.jpg (33.2 KB, 6362 views)
__________________

Last edited by Colm Moore : 05-09-2009 at 16:03.
Colm Moore is offline   Reply With Quote
Unread 05-09-2009, 19:23   #10
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Here is the step
Name:  Image000.jpg
Views: 7753
Size:  129.6 KB
Mark Gleeson is offline   Reply With Quote
Unread 05-09-2009, 19:40   #11
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

That breaks more rules than you can shake a stick at.
__________________
Colm Moore is offline   Reply With Quote
Unread 11-09-2009, 10:03   #12
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

The RSC are looking into it.

Quite a few other issues have arisen as well with the station, problems with lighting and other safety/security issues. The northbound stairs and booking hall where in darkness last night.

Needless to say we have had written correspondance with Irish Rail in the recent past, but the response time is crazy until something is done.
Mark Gleeson is offline   Reply With Quote
Unread 14-09-2009, 10:19   #13
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

So here is the situation on Friday night, they finally installed the two missing lamp posts, but then left the bridge in total darkness
Name:  Seapoint-ByNight-2.jpg
Views: 7759
Size:  175.1 KBName:  Seapoint-NoLights.jpg
Views: 7791
Size:  164.7 KB
Mark Gleeson is offline   Reply With Quote
Unread 16-09-2009, 08:06   #14
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

The RSC inspector has visited, and guess what all the lights are now working and the step, well see for yourselves
Name:  Image008.jpg
Views: 7734
Size:  116.7 KB
Mark Gleeson is offline   Reply With Quote
Unread 16-09-2009, 08:07   #15
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Better, but still doesn't comply.
__________________
Colm Moore is offline   Reply With Quote
Unread 28-09-2009, 11:18   #16
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

The southbound platform information display has awoken again, its a bit unsure of the current time but the train information is correct
Mark Gleeson is offline   Reply With Quote
Unread 08-10-2009, 15:50   #17
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

The fun continues, the booking office has been gutted by the builders, despite the plans showing it was to remain where it was

Ticket vending machine is unavailable as well as a result.

The southbound platform display has given up again
Mark Gleeson is offline   Reply With Quote
Unread 28-10-2009, 15:16   #18
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Still no booking office, looks like it will be one of the split height counters if it is ever finished
Mark Gleeson is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 00:54.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.