Engineering Works and delayed trains
Hi,
The last few weeks any of the trains I get (including the normally punctual & reliable 6.50am Sallins to Heuston) are at least 10 - 15 mins late arriving to Sallins. Is this due to the engineering works or because they are taking it easy on the 29000s because the can't get them to Drogheda for a service? Or is IR on a go slow(er)? Thanks. |
29-09-2009, 22:03 | #2 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
New signaling at Sallins is the problem, it causes a pinch point
__________________
Unhappy with new timetable - let us know |
30-09-2009, 19:18 | #3 |
New to the board
Join Date: Dec 2006
Location: Nás Na Ríogh
Posts: 18
|
Any idea as to when it will be fixed? The train this morning was waiting just outside the station for about 3 minutes. A total of 15 minutes late today...
|
30-09-2009, 20:26 | #4 |
Technical Officer
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
|
New signaling is between Sallins and Kildare its much higher capacity than the current Sallins - Adamstown section so you get a back log
The Sallins - Cherry Orchard section will be commissioned piece by piece in the next few months
__________________
Unhappy with new timetable - let us know |
30-09-2009, 21:05 | #5 |
New to the board
Join Date: Dec 2006
Location: Nás Na Ríogh
Posts: 18
|
Cheers Mark. Thanks for prompt reply!
|
01-10-2009, 19:52 | #6 |
Member
Join Date: May 2006
Location: Dublin
Posts: 608
|
Even the 07:10 to Galway has lost 10-15 minutes every morning for the past few weeks by the time it gets to Tullamore. Did you say "new signalling" and "pinch point"???? Are they going to fix it?