Default Enfield

I note Meath Co. Co. have granted planning subject to conditions for a footbridge at Enfield. Unfortunately the crap planning system does not appear to give access to the drawings etc. (app no TA111171). Is this just enhanced access or have they a notion of putting a 2nd platform in?
dowlingm is offline   Reply With Quote
Unread 19-04-2012, 20:51   #2
Traincustomer
Member
 
Join Date: Dec 2008
Location: ar an traein
Posts: 602
Default

Interesting. The second platform is a little overgrown in parts and would need some (but not massive) attention to bring it up to an useable standard. It is not as long as the platform that is used and appears a little low. Given the signal cabin building on that side is disused (well for signalling purposes in any case) there is a possibility of enhanced access or bringing the platform back into use.
Traincustomer is offline   Reply With Quote
Unread 20-04-2012, 14:09   #3
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Reads as a full section M footbridge, but with ramps instead of lifts which massively reduces costs

The platform will need a total rebuild as it will be slightly too low and missing tactile paving, lighting and drainage, it will also need to be 170m long. No planing application will be require for that
Mark Gleeson is offline   Reply With Quote
Unread 23-04-2012, 10:52   #4
cullenswood
Regular Poster
 
Join Date: Jul 2008
Posts: 34
Default

Quote:
Originally Posted by Mark Gleeson View Post
Reads as a full section M footbridge, but with ramps instead of lifts which massively reduces costs

The platform will need a total rebuild as it will be slightly too low and missing tactile paving, lighting and drainage, it will also need to be 170m long. No planing application will be require for that
Will this have any beneficial impact on scheduling to Enfield and further when it is complete?
cullenswood is offline   Reply With Quote
Unread 23-04-2012, 13:31   #5
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Short term no impact, but when trains are delayed it means things will move a lot better than before

For Enfield passengers likely to mean several more services

Future timetables will no longer have the restriction at Enfield.

That leaves us with only Millstreet and Clara as the only two odd stations with 1 platform but two tracks
Mark Gleeson is offline   Reply With Quote
Unread 23-04-2012, 15:55   #6
Colm Moore
Local Liaison Officer
 
Colm Moore's Avatar
 
Join Date: Dec 2006
Posts: 5,442
Default

Roscrea?

EDIT: Roscrea seems to have two tracks and two platforms, but only one is usable.
__________________

Last edited by Colm Moore : 23-04-2012 at 16:29.
Colm Moore is offline   Reply With Quote
Unread 23-04-2012, 17:51   #7
neoncircles
Member
 
Join Date: Jul 2009
Location: Limerick
Posts: 87
Default

Birdhill also
neoncircles is offline   Reply With Quote
Unread 24-04-2012, 00:18   #8
dowlingm
Really Really Regluar Poster
 
dowlingm's Avatar
 
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
Default

Woodlawn too?
dowlingm is offline   Reply With Quote
Unread 24-04-2012, 09:52   #9
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Woodlawn has the unique aspect of a single platform and was only recently given a loop
Mark Gleeson is offline   Reply With Quote
Unread 24-04-2012, 10:57   #10
comcor
Really Regular Poster
 
Join Date: Dec 2005
Location: Cork-Dublin, Cork Commuter and occasionally DART and Dublin-Wexford
Posts: 855
Default

Millstreet's loop is fairly new too isn't it? Last 5 years or so.
comcor is offline   Reply With Quote
Unread 24-04-2012, 11:09   #11
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Woodlawn was crazy in the sense it had no loop, but two trains could pass there
Mark Gleeson is offline   Reply With Quote
Unread 27-04-2012, 08:38   #12
James Howard
Really Really Regluar Poster
 
James Howard's Avatar
 
Join Date: Aug 2009
Location: Sligo Line
Posts: 1,115
Default

It should help enormously having the crossing at Enfield unconstrained it is the only crossing point between Maynooth and Killucan which must be about 50km.

The biggest delay problem on the Sligo line is the 17:00 Sligo-Dublin train that causes chaos in leafslip season because it has to cross with about 5 other trains. Since this isn't scheduled to stop at Enfield anyway, I can't see this being much help except that it allows an opportunity to offload the passengers into a bus or a couple of taxis and leave the train at Enfield until the 19:05 down train has passed.

But this will be a help and I must say that Irish Rail seem to have spectacularly gotten their act together on Sligo line delays since Christmas. I have had to alter my route home from the station because the train is routinely 3 or 4 minutes early at Edgeworthstown and so keeps the level crossing closed while it waits for the departure time.
James Howard is offline   Reply With Quote
Unread 31-07-2020, 02:58   #13
dowlingm
Really Really Regluar Poster
 
dowlingm's Avatar
 
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
Default

Did this ever get built? If I read Google Maps correctly it looks like “no”. Maybe IE felt the 6 (undetailed) conditions were unacceptable / outside their budget.
dowlingm is offline   Reply With Quote
Unread 05-08-2020, 06:02   #14
James Howard
Really Really Regluar Poster
 
James Howard's Avatar
 
Join Date: Aug 2009
Location: Sligo Line
Posts: 1,115
Default

It hasn't been built. It's quite mad really, when you look at all the development going up in Kilcock - the same should be happening in Enfield with a peak-time extension for the Maynooth commuter service.
James Howard is offline   Reply With Quote
Unread 06-08-2020, 11:12   #15
comcor
Really Regular Poster
 
Join Date: Dec 2005
Location: Cork-Dublin, Cork Commuter and occasionally DART and Dublin-Wexford
Posts: 855
Default

Is Enfield a realistic place to terminate any service without creating a third platform, not just a second? (I note that there seems to be the remains of a siding that could accommodate that).

Or once you've got that far, do you just continue to Mullingar, which is as far out of Dublin as Dundalk and Port Laoise, which both have comuter services?
comcor is offline   Reply With Quote
Unread 06-08-2020, 11:43   #16
berneyarms
Really Regular Poster
 
Join Date: Aug 2013
Posts: 602
Default

Quote:
Originally Posted by comcor View Post
Is Enfield a realistic place to terminate any service without creating a third platform, not just a second? (I note that there seems to be the remains of a siding that could accommodate that).

Or once you've got that far, do you just continue to Mullingar, which is as far out of Dublin as Dundalk and Port Laoise, which both have comuter services?
Perfectly possible to turn trains at Enfield as it is a block post - just depends on the overall schedule so that there aren’t other trains clashing on the single track.
berneyarms is offline   Reply With Quote
Unread 06-08-2020, 21:04   #17
Jamie2k9
Really Really Regluar Poster
 
Join Date: Jun 2010
Posts: 2,146
Default

Slighly suprising Enfeild loop lasted over recent years, 7 years with no scheduled use. IE attatitue is use them or lose them!

It was only braught back into use when the 06.55 resumed.

Last edited by Jamie2k9 : 06-08-2020 at 21:07.
Jamie2k9 is offline   Reply With Quote
Unread 10-08-2020, 09:11   #18
comcor
Really Regular Poster
 
Join Date: Dec 2005
Location: Cork-Dublin, Cork Commuter and occasionally DART and Dublin-Wexford
Posts: 855
Default

I suppose my point was more whether it was a good idea. I guess longer distance traffic on the Sligo line is rare enough that it can be scheduled to avoid disrupting that traffic. It’s not a conversation we could have about the Kildare line.

The ideal situation here is to have a stopping train from Dublin arrive and pull into a third platform, just ahead of an InterCity from Dublin and an InterCity from Sligo, with passengers from intermediate stations heading to Longford, Sligo etc. able to change. Then it sets off to Dublin with any connecting passengers from places further down the line to stations en route. The relative lack of complexity on the Sligo line compared to the lines ex-Heuston, which split and split again, means it’s something that can work relatively well on it. It looks like Enfield would at least have the space to build for such a scenario, even if we can only dream of those levels of connectivity.
comcor is offline   Reply With Quote
Unread 11-08-2020, 18:32   #19
ACustomer
Really Regular Poster
 
Join Date: Jan 2006
Posts: 767
Default

comcor: something like you are advocating already occurs at Maynooth. Most Dublin-Sligo trains arrive at Maynooth a few minutes after a suburban train and picks up passengers from intermediate stations. Its the same with up trains: you can generally get off a train from Sligo at Maynooth and pick up a stopping suburban train about 7 or 8 minutes later.
Is quite a neat arrangement and any issue with Enfield is a largely separate matter
ACustomer is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 15:33.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.