View Single Post
Unread 16-04-2008, 13:02   #3
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Once again another screw up, despite new track, new signaling and new trains the Sligo line is no better than the bad old days, in fact its probably worse

There is meant to be an emergency generator at each signaling location to deal with power failures, needless to say these frequently don't start due to poor maintenance

There are fairly strict procedures to swiftly deal with total signaling failures, there is a gate keeper on duty in Clonsilla who would be more than able to walk down the line to manually operate the level crossing beyond Clonsilla
Mark Gleeson is offline   Reply With Quote